Home News Local News

Bid approved for city greenhouse

Council applies for grants for two street projects.
Richard Hanners

Blue Mountain Eagle

Published on July 31, 2018 5:05PM

From left, Councilors Dave Holland and Paul Smith watch a presentation on the city’s strategy for growth during the city council’s July 24 meeting.

The Eagle/Richard Hanners

From left, Councilors Dave Holland and Paul Smith watch a presentation on the city’s strategy for growth during the city council’s July 24 meeting.

Buy this photo
John Day City Manager Nick Green describes progress in the city’s strategy for growth during the city council’s July 24 meeting.

The Eagle/Richard Hanners

John Day City Manager Nick Green describes progress in the city’s strategy for growth during the city council’s July 24 meeting.

Buy this photo
From left, Councilors Brandon Smith and Gregg Haberly watch a presentation on the city’s strategy for growth during the city council’s July 24 meeting.

The Eagle/Richard Hanners

From left, Councilors Brandon Smith and Gregg Haberly watch a presentation on the city’s strategy for growth during the city council’s July 24 meeting.

Buy this photo
John Day is considering purchasing a commercial greenhouse from EuroMex, a company that manufactures very large commercial greenhouses like the one shown in this contributed image.

Contributed photo

John Day is considering purchasing a commercial greenhouse from EuroMex, a company that manufactures very large commercial greenhouses like the one shown in this contributed image.

John Day is considering purchasing a commercial greenhouse from EuroMex, a company that manufactures very large commercial greenhouses like the one shown in this contributed image.

Contributed photo

John Day is considering purchasing a commercial greenhouse from EuroMex, a company that manufactures very large commercial greenhouses like the one shown in this contributed image.


The city of John Day moved ahead last week with commercial greenhouse plans for the Innovation Gateway site at the city’s west entrance.

The city council approved a notice of intent to award EuroMex, headquartered in Spain with offices in Los Angeles and Mexico, a $337,590 bid for a 6,240-square-foot greenhouse that will produce about 30 tons of produce per year, meeting the city’s demand.

EuroMex, which typically builds large facilities, outscored Clearspan, City Manager Nick Green said. The greenhouse’s three 16-foot high, 26-by-80-foot bays will have clear walls so visitors can view the facility without going inside and possibly contaminating the environment.

Green said EuroMex will send personnel to John Day to install electronics and oversee city crews who will assemble the greenhouse. If the project works out, the city could build additional greenhouses and start exporting produce, Green said.

The city council will take up the EuroMex bid at its Aug. 14 meeting. The project will be reviewed by the Grant County Planning Commission later in August because the 2-acre site lies outside the city limits.


Street projects


In a busy meeting, the council also picked two street projects to apply for funding from Oregon Special City Allotment grants, which recently increased from $50,000 per year to $200,000 for two separate projects. The deadline for submitting the grant application was Aug. 1.

The council agreed to apply for the grant funding to extend Valley View Drive to Patterson Bridge Road near the Malheur National Forest building, which would provide access to street networks within Phase 2 of Ironwood Estates.

This street plan was approved earlier by the city. Joe Hitz of Sisul Engineering said the road is about 80 percent built and estimated completion costs at $282,000.

The council also agreed to reconfigure and rebuild the intersection of Charolais Drive, Valley View Drive, Bridge Street and two other streets. Valley View and Bridge Street would become a through-street. Green noted that parking for the future Davis Creek trail system and botanical gardens would be located near this intersection.

Engineering for this project was completed, and John Day Public Works Director Monte Legg said the Grant County Road Department was still on board to assist. Hitz estimated the cost to complete the project at $244,000.

The option to extend Seventh Street west from Bridge Street to Patterson Bridge Road was turned down because it’s too early and too expensive. Extending Seventh Street would provide access to Innovation Gateway from the north side of the river and provide a second bridge connection for the city’s north side.

The design, however, is not final because the city’s new sewer treatment plant has not been sited, and the city was not sure what will happen to the existing percolation ponds, Green said.

The street project is also very complex and expensive. According to preliminary plans, the middle segment calls for wider lanes, a landscaped median, parallel parking, a 200-foot bus turnaround circle, four special parking spaces for buses and street lights. Fully developed, the estimated cost is $3.2 million.

Another option turned down by the council called for various chip-sealing projects. With the county already doing chip-sealing projects this year, Legg suggested holding off chip-sealing until 2020.


Recreation plans


The council also moved ahead with several long-range plans for city parks and trails.

Green was directed to continue negotiations with the Oregon Department of Parks and Recreation for the sale of 3 acres of city land adjacent to the Kam Wah Chung State Heritage Site.

The state wants to use the land, which includes Gleason Pool, to build a new interpretive center. Chris Labhart, who works at the museum, said the state might pay $1 million for the city land.

The council also authorized Green to sign a purchase and sales agreement for 10 acres of land on both sides of the John Day River near Canyon Creek owned by Colleen and Celeste Hill.

The 4-acre property on the south side of the river would be used for a new city park. Green noted that additional property needed for a trail along Canyon Creek linking the new park to Kam Wah Chung would be provided through lot-line adjustments.

Two neighbors, however, expressed security concerns if a public trail is built right along their backyards. They also noted that the city’s creekside property may be too narrow in places for a new trail.

Lastly, the council approved a $17,500 feasibility study agreement with consultant Counsilman-Hunsaker for options for a possible new aquatic center to replace Gleason Pool. Green assured Mayor Ron Lundbom that the funding was available and said he hopes to leverage the $17,500 into a regional investment to attract people to John Day.

The city council’s next meeting is Aug. 14.